Fire alarm cable in Canada: what the electrical code and CAN/ULC-S524 actually require
Fire alarm cable in Canada is governed by Section 32 of the Canadian Electrical Code, adopted in Ontario as the Ontario Electrical Safety Code, which requires copper conductors rated not less than 300 V, a minimum of No. 16 AWG for individual insulated conductors pulled into a raceway and No. 19 AWG for individual insulated conductors laid in a raceway, and requires those conductors to be kept entirely independent of all other wiring. The cable itself is built to CSA C22.2 No. 208, which is where the FAS and FAS 105 markings on the jacket come from, and its flame rating is a CSA FT number rather than an American CMP or CMR designation. Because a fire alarm is a safety control device, the circuit is treated as Class 1 even at 24 V. CAN/ULC-S524 governs how the system is installed, and the Building Code is what required it.
Last updated: September 2026
Quick answer
- Copper conductors, insulation rated not less than 300 V. Ordinary Class 2 control cable is often rated lower and will not pass.
- Minimum No. 16 AWG for individual conductors pulled into a raceway, No. 19 AWG for individual conductors laid in a raceway, and No. 19 AWG for an integral assembly of two or more.
- Conductors must be entirely independent of all other wiring, and must not enter a raceway, box or enclosure occupied by other wiring.
- The circuit is treated as Class 1 even at 24 V, because a fire alarm is a safety control device.
- The cable is built to CSA C22.2 No. 208, which is where FAS, FAS 90 and FAS 105 on the jacket come from. Maximum 300 V, minimum 60 °C.
- The flame rating is a CSA FT number, not an American CMP or CMR. FT6 is the Canadian plenum grade.
- Where a circuit has to survive fire, the Ontario Building Code points at CAN/ULC-S139 and a 1 h circuit integrity rating, or a 1 h fire separation instead.
Which document governs which part of the job
Three documents touch a fire alarm cable pull, and mixing them up is the most common reason a job gets argued about on site.
The Building Code is what makes you install a system at all, and it is the document that names the ULC standards. On how the two codes divide up, see Building Code versus Fire Code in Ontario.
CAN/ULC-S524 governs the design and installation of the system itself: circuit classes, supervision, zoning, device placement, what a fault has to do. Its scope covers both code-required and voluntary installations. The current published edition is CAN/ULC 524:2024, the 8th edition, but the codes in force still reference the 2019 edition, and that distinction matters more than people expect. See which edition applies.
The Canadian Electrical Code, Part I, Section 32, governs the wiring method and the conductors. In Ontario it is adopted as the Ontario Electrical Safety Code. The 2024 OESC came into force 1 May 2025, it is the 29th edition, and it contains the 26th edition of the Canadian Electrical Code, Part I, plus Ontario-specific amendments. Some sources, ESA's own pages included, call it the 28th edition; the OESC glossary entry settles the number and explains where the confusion comes from.
So: the Building Code tells you a system is required, S524 tells you how the system goes together, and Section 32 tells you what wire you are allowed to put in the pipe. An inspector on one of those documents cannot sign off the other one.
The conductor rules you have to hit
These are the numbers to have in your head before you order anything. Fire alarm conductors are copper, with ampacity adequate for the circuit, and an insulation rating of not less than 300 V. Optical fibre is permitted as an alternative.
Minimum sizes split three ways, and the split is about how the conductor gets into the raceway:
- No. 16 AWG for individual insulated conductors pulled into raceways
- No. 19 AWG for individual insulated conductors laid in raceways
- No. 19 AWG for an integral assembly of two or more insulated conductors
The logic is mechanical. A conductor dragged through a pipe takes tension and abrasion that a conductor laid into a trough never sees, so it has to be heavier. An assembly gets the benefit of its own jacket.
Source note. The three sizes are cited to Rule 32-100(4) by Ark Tsisserev in IAEI Magazine's Canadian Perspectives column, Summer 2025. The copper, 300 V and raceway-sizing elements are independently corroborated by William Burr's road map to Section 32 of the 26th edition of the CE Code in Electrical Industry News Week. Both are Canadian-authored secondary sources; the code text is paywalled and we did not read it. If you are putting a rule number into a compliance document, check it against your own copy of the OESC.
A practical point follows from the 300 V rating: the general-purpose 18/2 and 16/2 control cable on the van from another trade is frequently rated below it. It is not fire alarm cable in Canada, however convenient, and swapping it in is a deficiency an inspector will find without trying.
Why a 24 volt circuit is treated as Class 1
Everything about a fire alarm initiating circuit invites you to treat it as low voltage you can run loosely. It is 24 V, and it draws milliamps. In most other trades that would be the end of the analysis.
The Canadian code closes that door explicitly. Rule 16-010 requires that a circuit supplying a safety control device, where failure of that device would introduce a direct fire or life hazard, be deemed a Class 1 circuit regardless of the voltage or whether the supply is power limited. A fire alarm system is exactly that kind of device.
None of the relaxations you would reach for on a Class 2 circuit are therefore available. Not the lighter wiring methods, not the loose separation, not the smaller conductors. This is one of the sharper divergences from American practice, where fire alarm circuits are commonly installed as power limited under a different rule set entirely. American guidance on power limited fire alarm cable does not transfer here, and we treat that divergence at length in NFPA 72 versus CAN/ULC-S524.
Permitted wiring methods under Section 32 are, in summary: totally enclosed metal raceway, cable with metal armour or a metal sheath, rigid non-metallic conduit, and electrical non-metallic tubing embedded in masonry or concrete. The theme is mechanical protection.
Reading the jacket: FAS, FT and what listing means
Canadian fire alarm cable is built to CSA C22.2 No. 208, Fire alarm and signal cable, currently C22.2 No. 208:18. Its scope, published openly by the Standards Council of Canada, covers single and multiple conductor fire alarm cables with a maximum nominal voltage rating of 300 V and a minimum temperature rating of 60 °C, and defines five construction types:
FAS, FAS 90, FAS 105, FAS 150 and FAS 200.
The number is the temperature rating in degrees Celsius, so FAS 105 is 105 °C rated cable, and it is what you will see most often on Canadian jobs. There is nothing magic about the 105: it is not a fire survivability rating, it is not a riser rating, and it tells you nothing about flame spread.
Flame spread is separate and appears as an FT marking. On a Canadian jacket you should be able to read, in some order: the type designation (FAS 105), the voltage rating (300 V), the conductor count and size, the FT rating, and a certification mark.
That certification mark is what "listed" means in practice. The cable has to be certified by a body accredited by the Standards Council of Canada, and the mark on the jacket is the evidence. A US-only UL mark is not a Canadian certification: see ULC versus UL in Canada. If the jacket carries no Canadian mark it does not go in the building.
Riser and plenum, and why the American names do not map
If you have come from American supply catalogues you are used to CMP for plenum, CMR for riser and CM for general purpose. Canada does not use those designations. It uses CSA FT ratings, which come from different tests.
| Rating | Test | Rough American equivalent |
|---|---|---|
| FT1 | Vertical flame test | general purpose |
| FT2 | Horizontal flame test | general purpose |
| FT4 | Vertical tray test, CSA C22.2 No. 38, aligned with IEEE 1202 | CMR, riser |
| FT6 | Steiner tunnel test under CSA C22.2 No. 0.3 | CMP, plenum |
FT6 is the Canadian plenum grade. It is the most stringent of the set, and it is what belongs in a ceiling void used as a return air plenum or in any other air-handling space.
The requirement does not originate in the electrical code. It originates in the National Building Code, which restricts materials in air-handling plenums to a flame spread rating not exceeding 25 and a smoke developed classification not exceeding 50, with defined exceptions for qualifying electrical cables and raceways. The CE Code implements that through Rules 2-130 and 2-132. Ark Tsisserev's IAEI column sets that chain out, but his article dates from 2019, so confirm the rule numbers against your current edition.
Canadian Consulting Engineer records that Ontario and British Columbia opted for the more stringent FT6 requirement. Treat that as background, not as your compliance answer, because what counts as a plenum is a building question before it is a cable question. The practical failure is ordering FT4 for a job where the ceiling void turns out to be a return plenum, and finding out after the ceiling is closed.
Shielded or unshielded, and the mistake that costs you a morning
Shielding on a fire alarm job is almost always about data, not the initiating circuit. Twisted shielded pair is typically specified for RS-485 style data buses between a panel and its transponders or annunciators, with power run as a separate pair. Running data and power in one common jacket is a reliable way to generate intermittent faults nobody can find.
Here is what we could not verify, and we would rather say it than guess. We could not locate a requirement in CAN/ULC-S524 or in Section 32 that specifies when a shield is required or how it is to be terminated. The standards are paywalled, and the free Canadian secondary sources we read defer the question to the equipment manufacturer's installation instructions. In practice those instructions are the operative document.
What is not in dispute is the field error. Grounding a shield at both ends creates a ground loop. The shield becomes a parallel path between two points that are not at the same potential, and current circulates through it. The symptoms are exactly the ones that waste a morning: intermittent communication faults on the data bus, a ground fault that appears and clears with no obvious cause, and behaviour that changes when a piece of unrelated equipment on the same building steel switches on.
The same failure happens without anyone grounding anything on purpose, when a drain wire is left long inside a device box and touches the box or a bonded mounting screw. That is one accidental second ground, and it produces the identical symptoms.
The discipline is simple: ground the shield at one end only, normally at the panel, and cut back and insulate the drain wire at every other termination so it cannot find metal. If you are chasing a fault that fits this description, our guide to ground fault troubleshooting walks through isolating it, and the shielded cable entry covers the terminology.
When the cable has to survive the fire
Some circuits are expected to keep working while the building burns, and that is where circuit integrity cable comes in.
In Ontario the relevant provision is Article 3.2.7.10, Protection of Electrical Conductors. Conductors serving certain systems must either conform to CAN/ULC-S139 and provide a circuit integrity rating of not less than 1 h, or run in a service space separated from the rest of the building by a fire separation with a fire-resistance rating of not less than 1 h. Certain mechanical applications call for 2 h instead. There is an important carve-out: fire alarm branch circuits within a storey that connect transponders and individual devices do not have to meet it.
CAN/ULC-S139 is the Standard for Fire Test for Circuit Integrity of Fire-Resistive Power, Instrumentation, Control, and Data Cables. It is a binational standard with requirements identical to ANSI/UL 2196, and it tests cables energised during fire exposure and then hit with a hose stream. The 2017 edition has been superseded by CAN/ULC 139:2025.
Be aware of the limits of what we can tell you here. We read Article 3.2.7.10 in two secondary reproductions of the Ontario Building Code, one presented as the 2024 edition (O. Reg. 163/24) and one as the 2012 and 2017 editions. The substance agrees, but we could not open the free Building Code Compendium to confirm the numbering as it stands in the 2024 Code, so confirm it before you cite it. And where a specification calls for two hour survivability on a fire alarm circuit, that often comes from the specification or the S524 design rather than a Building Code article. Ask which, because the answer changes what you may substitute.
Separation, shared raceways and shared boxes
This is the requirement that produces the most arguments and the most rework. Fire alarm conductors must be installed entirely independent of all other wiring, and must not enter a raceway, box or enclosure occupied by other wiring. The exceptions are the defined connection points: the point of supply, signal, ancillary device and communication circuit connections.
Read that literally, because it is meant literally. It is not "keep them apart where practical". A shared 4 by 4 box with a lighting circuit is a failure. A shared piece of EMT is a failure. A fire alarm cable passing through a junction box that holds line voltage, with no splice made, is still a failure: the rule is about occupancy of the enclosure, not about whether you connected anything.
The inspection failures that follow are predictable:
- Fire alarm cable pulled into a spare conduit that already carries a lighting circuit, because the pipe was there
- A ground fault traced back to a fire alarm conductor abraded against a line voltage conductor in a shared box
- Devices fed from a junction box shared with an unrelated system, found at verification rather than rough-in
- Non-metallic wiring methods installed with no bonding conductor
Where a shared pathway genuinely cannot be avoided, that is a conversation with the authority having jurisdiction before you pull, not a defence after the fact.
Quick reference
| Item | Requirement | Verified? |
|---|---|---|
| Conductor material | Copper. Optical fibre permitted as an alternative | Two Canadian sources agree |
| Insulation rating | Not less than 300 V | Two Canadian sources agree, and consistent with C22.2 No. 208 |
| Individual conductor pulled into raceway | Minimum No. 16 AWG | One source, rule cited as 32-100(4) |
| Individual conductor laid in raceway | Minimum No. 19 AWG | One source, rule cited as 32-100(4) |
| Integral assembly, two or more conductors | Minimum No. 19 AWG | One source, rule cited as 32-100(4) |
| Independence from other wiring | No shared raceway, box or enclosure except at defined connection points | Two Canadian sources agree |
| Circuit class | Class 1 regardless of voltage or power limitation | One source, rule cited as 16-010 |
| Cable product standard | CSA C22.2 No. 208, types FAS to FAS 200 | Verified, SCC published scope |
| Plenum grade | FT6 | Grade verified; where it is required is a building code question |
| Riser grade | FT4, closest equivalent to American CMR | Canadian secondary source |
| Circuit integrity | CAN/ULC-S139, 1 h rating, or 1 h fire separation | Standard verified; OBC article number needs confirming |
Sizing a conductor for the code minimum is not the same as sizing it for the job. On a long notification circuit the governing constraint is voltage drop, not the code minimum, and you size up accordingly.
What we could not confirm
- The Section 32 rule numbers. The requirements are attested by two independent Canadian sources, one of them keyed to the 26th edition of the CE Code. The numbers 32-100, 32-100(4), 32-102, 32-102(3) and 16-010 come from those secondary sources, not from code text we read. Ontario amendments could differ.
- Shielding requirements in CAN/ULC-S524. We could not locate any. The shield practice above is field practice plus manufacturer instruction, not a rule we can cite.
- The article and sentence numbering of the Ontario Building Code circuit integrity provision in the 2024 edition. The substance is consistent across the reproductions we read. The numbering is not confirmed against the 2024 Compendium.
- Whether Ontario mandates FT6 in every plenum space. A Canadian trade source states Ontario and BC opted for FT6. We could not confirm the current provision.
Confirm all of the above with your electrical inspector and the authority having jurisdiction on the specific project. If you are ordering cable for a job where the answer matters, ask before the purchase order, not after the pull.
Fire Alarm Academy provides educational content only. It does not confer any certification, licence or credential, and it is not affiliated with, endorsed by, or accredited by the Canadian Fire Alarm Association, the Electrical Contractors Association of Ontario, ULC Standards, UL Standards and Engagement, CSA Group, the Electrical Safety Authority, any authority having jurisdiction, or any manufacturer. Always work from the edition of any standard adopted by your authority having jurisdiction.
Frequently asked questions
What size wire do I need for a fire alarm circuit in Canada?
Copper, with an insulation rating of not less than 300 V, and not smaller than No. 16 AWG for an individual insulated conductor pulled into a raceway or No. 19 AWG for an individual insulated conductor laid in a raceway. An integral assembly of two or more insulated conductors has a minimum of No. 19 AWG. On long notification circuits voltage drop usually forces you larger than the minimum anyway.
Can I use regular 18/2 thermostat or control cable for a fire alarm?
No. Fire alarm conductors need an insulation rating of at least 300 V and a minimum size of No. 16 AWG where pulled into a raceway, and the cable has to be a certified fire alarm cable built to CSA C22.2 No. 208. Most general purpose control cable fails on the voltage rating alone.
What does FAS 105 mean on a fire alarm cable jacket?
FAS is the Canadian type designation for fire alarm and signal cable under CSA C22.2 No. 208, and the number is the temperature rating in degrees Celsius, so FAS 105 is rated to 105 °C. It is not a fire survivability rating and it tells you nothing about flame spread, which is shown separately as an FT number.
Is FT6 the same as plenum cable in Canada?
Yes, FT6 is the Canadian plenum grade. It is tested in the Steiner tunnel under CSA C22.2 No. 0.3 and is the rough equivalent of the American CMP designation, while FT4 is the vertical tray test and is closest to American CMR. Canada does not use the CMP and CMR names.
Can fire alarm cable share a conduit or a junction box with power wiring?
No. Fire alarm conductors must be installed entirely independent of all other wiring and must not enter a raceway, box or enclosure occupied by other wiring, apart from defined connection points such as the point of supply and communication circuits. It is about occupancy of the enclosure, so an unspliced fire alarm cable passing through a shared box is still a failure.
Should I ground the shield on fire alarm data cable at both ends?
No. Ground the shield at one end only, normally at the panel, and cut back and insulate the drain wire at every other termination. Grounding at both ends, or letting a long drain wire touch a bonded box or screw, creates a ground loop that shows up as intermittent communication faults and phantom ground faults.
When does a fire alarm circuit need fire-rated survivability cable in Canada?
The Ontario Building Code requires certain conductors to either meet CAN/ULC-S139 with a circuit integrity rating of not less than 1 h or to run in a service space with a 1 h fire separation, with 2 h required for some mechanical applications. Fire alarm branch circuits within a storey connecting transponders and individual devices are carved out. Confirm the article numbering against the 2024 Building Code before citing it.
Which edition of the Ontario Electrical Safety Code applies right now?
The 2024 Ontario Electrical Safety Code came into force 1 May 2025. It is the 29th edition and contains the 26th edition of the Canadian Electrical Code, Part I, plus Ontario amendments. Some sources, ESA's own pages included, call it the 28th edition; the OESC glossary entry at /glossary/oesc settles the number and explains where the confusion comes from.
Sources
- CSA Group catalogue: Ontario Electrical Safety Code, 29th Edition, 2024, stating it contains the 26th edition of the Canadian Electrical Code, Part I
- Electrical Safety Authority: 2024 Ontario Electrical Safety Code comes into effect 1 May 2025
- IAEI Magazine, Canadian Perspectives, Ark Tsisserev: Canadian fire alarm conductor sizes, 300 V insulation, Rule 16-010 Class 1 deeming, Rule 32-102 separation (secondary)
- Electrical Industry News Week, William Burr: road map to Section 32 of the 26th edition Canadian Electrical Code (secondary)
- Standards Council of Canada: scope of CSA C22.2 No. 208:18, Fire alarm and signal cable, 300 V maximum, types FAS through FAS 200
- Standards Council of Canada: CAN/ULC-S139:2017, Fire Test for Circuit Integrity of Fire-Resistive Power, Instrumentation, Control, and Data Cables, superseded by CAN/ULC 139:2025
- Standards Council of Canada: CAN/ULC-S524, Standard for Installation of Fire Alarm Systems, scope covering required and voluntary installations
- IAEI Magazine, Canadian Perspectives, Ark Tsisserev 2019: CE Code Rules 2-130 and 2-132, FT4 and FT6 in plenums, and National Building Code Article 3.6.4.3 (secondary)
- Sycor Technology, Canadian supplier: CSA flame test ratings FT1 to FT6, test standards and American equivalents (secondary)
- Canadian Consulting Engineer: history of FT4 and FT6 adoption, noting Ontario and British Columbia opted for FT6
- CodeIndex reproduction of Ontario Building Code Article 3.2.7.10, Protection of Electrical Conductors, presented as the 2024 Code, O. Reg. 163/24 (secondary)
- Fire Protection Technicians Network: CAN/ULC-S524 field device installation guideline, on twisted shielded pair for data buses and deferral to manufacturer instructions (secondary)
Related guides
Powering a Fire Alarm System: What CEC Section 32 Requires
Fire alarm circuits in Canada are governed by Section 32 of the Canadian Electrical Code, and they are held to a stricter standard than ordinary low-voltage control wiring. The panel gets its own dedicated circuit with a permanently marked, red disconnect that locks in the ON position. Conductors are copper, rated at least 300 V, and must be kept independent of all other wiring. And because a fire alarm is a safety control device, its circuits are treated as Class 1 regardless of voltage or power limitation.
Fire Alarm Ground Fault Troubleshooting: A Canadian Walkthrough
A ground fault on a fire alarm circuit is an unintended low resistance path between a field conductor and grounded metalwork, and the panel reports it only because a dedicated ground fault detector in the control unit watches the field wiring for leakage to earth. In Canada that visibility comes from the supervision requirements: the Building Code requires electrical supervision of the fire alarm system, and CAN/ULC-S524 requires that a single open, short or ground fault not stop devices operating in more than one Building Code required zone. You locate it by half-splitting: lift all field wiring at the panel to prove panel against field, reconnect circuits one at a time to identify the affected circuit, then split that circuit at its midpoint in wiring order and keep halving. In Ontario, doing this on a system already in service is Fire Code work under Division C Article 1.2.1.2 of O. Reg. 213/07, a separate permission from the 309A certificate that covers the installation.
Which Edition of the Standard Actually Applies to Your Job?
The newest published standard is almost never the one you build to. CAN/ULC 524:2024 (the 8th edition of the installation standard) was published in December 2024. The codes in force across Canada still reference the 2019 editions, and Ontario only reached the 2019 editions of S536 and S537 on 1 January 2026. Citing "CAN/ULC-S524" with no edition in a compliance document means nothing. The edition that governs is the one your authority having jurisdiction has adopted.
ULC vs UL: What Actually Counts in Canada
Almost every ULC-versus-UL argument on a job site is two different things being confused. A standard is a document, CAN/ULC-S524 is a document. A certification mark on a device says a certification body evaluated that device against a standard. Different organisations, different accreditations, different meanings. In Ontario the legal test for a product is not which logo it carries but whether the body behind that logo is accredited by the Standards Council of Canada, the Electrical Safety Authority states that outright. And as of 1 April 2025, ULC Standards is no longer a separate accredited standards developer: SCC merged its file into UL Standards & Engagement Inc. The CAN/ULC designations continue. The "CAN" in front of them is an SCC-mandated descriptor meaning National Standard of Canada; it is not part of ULC's brand.